Amazon Development - Off-Site Improvements
At the March 18, 2026 Village Board meeting, staff presented an overview of planned off-site improvements related to the Amazon development, including key construction phases and anticipated road impacts. The information presented was current as of March 3 and subject to change. Construction is expected to start Late March/Early April.
There are four planned construction phases:
- Stage 1 and 2, Full closure of CTH TT - Timeline is 2 to 2.5 months
- Stage 3, Full closure of CTH N - Approximate start on June 15 with completion mid-September, Dane County also reconstructing Koshkonong Creek Bridge separate from this project.
- Stage 4, Roundabout Surface Paving - Timeline is to be determined. This will include potential flagging operations.
Interstate ramp work and pavement markings will happen near the end of Stage 3.
All local residents, businesses, and emergency services will have full access during road closures.
Park and Ride will be accessible throughout construction.
Additional information on off-site improvements is available on the Village website.