Project Overview
The 2019 Cottage Grove Road Rehabilitation Project will take place during the 2019 construction season. This project will include pavement removal and replacement on Cottage Grove Road from Ollie Street to 400 feet east of Sandpiper Trail. Also included in the project are ADA improvements to the sidewalk curb ramps and the bike route. This work will include sidewalk and curb and gutter removal and replacement as well as extending the asphalt bike path to Southing Grange. During the duration of the project, the traffic on Cottage Grove Road within the project limits will be limited to one lane of travel in each direction.
Driveway Access
The Contractor is responsible to maintain access to active driveways within the project limits with the exception of the divided entrance at 421 W. Cottage Grove Road. This location will be closed for t he duration of the project to promote safe ingress and egress to Cottage Grove Road. Access to the driveway at 406 W. Cottage Grove Road (Abiding Shepard Lutheran Church) may be limited during the removal of the sidewalk and the placement of the asphalt bike path.
Mail Delivery
Mail deliver will not be affected.
Garbage Pickup
Garbage pickup will not be affected.
Project Planset
A copy of the project planset will be available for public viewing at Village Hall during normal business hours.
Current Project Schedule:
Project start date: June 17, 2019
Substantial Completion: August 15, 2019
Final Completion: August 29, 2019
Your patience and understanding throughout this project is appreciated.